On July 6th of 2020, the repaired tram number 258 leaves the Tradinsa facilities towards Edinburgh to deliver it to the customer Edinburgh Tram.

The Edinburgh tram consists of 7 cars (E, D, G, F, C, B, A), however only the cars E, D, G, F, C are damaged.

The main work carried out are:

  • 3D scan of carbody, underframe and bogie frame
  • Head Removal from Car E (Cab)
  • Car E (Cab) Composite Cell Repair
  • Replacing the glass, fairings, headlights and windshield wipers of car E (cabin)
  • Repair of turning stops and supports in the underframe area of ​​cars with bogie
  • Repair and / or replace skirts and fairings according to damage
  • Repair and / or replace according to the damage the end caps on the cars
  • End cap and Underframe Weld Repair Procedures
  • Review of frame of bogies and mounted bridges
  • Replacement of bogie bumpers
  • Replacement of tire treads
  • Exterior painted